School Refurbishment Cost
National benchmark rates, real contract values from public notices and a budget tool. A guide, not a quote.
What does the national benchmark say?
The National School Delivery Cost Benchmarking report is put together by Hampshire County Council, East Riding of Yorkshire Council and the Department for Education. Version 18, published in November 2023, includes 56 primary school refurbishment projects at 2023 prices.
Average primary refurbishment
£2,601 per m²
Heavy refurbishment
£2,898 per m²
Medium refurbishment
£2,082 per m²
Per pupil place
£18,253
Average floor area
1,130 m²
Average contract length
34 weeks
Rates are gross cost per square metre of floor area at tender stage. They include design fees, externals, abnormals, fittings, preliminaries, contingency, overheads and profit. They exclude VAT, statutory fees, surveys, loose furniture and client costs.
How much might your project cost?
Enter the floor area of the rooms and pick how deep the work goes. The tool multiplies by the benchmark rate. It is a starting point for a budget, not a price.
What have schools actually paid?
Contract values from award notices that councils and the DfE published on Contracts Finder. Each figure is the value of the whole contract, excluding VAT.
The middle value of the nine science lab jobs was £269,753. See the lab data study.
What pushes the price up or down?
Six things explain most of the difference between two quotes for the same rooms.
Depth of work
Decoration and flooring is a fraction of the cost of renewing heating, wiring and ceilings.
Services
Gas, water, drainage and ventilation are where lab, toilet and kitchen prices climb.
Asbestos
Surveys, removal and extra precautions in older buildings add cost and time.
Working hours
Holiday-only or after-hours working can mean more labour in a shorter window.
Phasing
Splitting a job across several holidays adds set-up and preliminaries each time.
Region and timing
The benchmark figures are at 2023 prices. Building costs have moved since, and vary by region.
What do schools ask about cost?
What does a whole-school refurbishment cost?
The national benchmark puts the average primary school refurbishment at £2,601 per square metre, or £18,253 per pupil place, at 2023 prices. A typical project was about 1,130 m², so well over two million pounds. Single rooms cost far less.
Do these figures include VAT?
No. The benchmark excludes VAT, statutory fees, surveys, loose furniture and the school's own costs. It includes design fees, fittings, preliminaries, contingency and the contractor's overheads and profit.
What about secondary schools?
The benchmark had too few secondary refurbishment projects to draw conclusions, so we have not quoted a secondary figure. Secondary jobs often include labs and workshops, which push the rate per square metre up.
Can we get government funding?
Some schools and colleges can bid to the DfE's Condition Improvement Fund. For 2027 to 2028, applications close at 12 noon on 15 December 2026. Projects start at £20,000 for primary and £50,000 for secondary, up to £4,000,000. Our blog post on CIF goes through it.
Where these figures come from
- National School Delivery Cost Benchmarking, version 18
- DfE: Condition Improvement Fund, information for applicants 2027 to 2028
- GOV.UK: apply for the Condition Improvement Fund
- Contracts Finder: Toilet refurbishment at three primary schools, London Borough of Lewisham
- Contracts Finder: Refurbishment for a new kitchen, Hadlow Rural Community School (DfE)
- Contracts Finder: The Toynbee School science lab
Get a quote for your refurbishment
Four boxes: the school postcode, who to ask for, a phone number and an email. That is enough for us to get going.
School Refurbishment Contractors is an independent matching service. We look for a refurbishment contractor that covers the school's area. You get the contractor's name first, and your details stay with us until you say yes. The school pays nothing.
Got it. We're on it.
What happens next:
- We search for a contractor that covers the school, then email you their name.
- You give the go-ahead, or tell us to stop. Nothing moves without your say.
- The contractor calls to book a visit to the rooms and then sends a written price.