What Schools Paid for Science Lab Refurbishments
Nine contracts let by one county council between 2021 and 2024, taken from the award notices it published on Contracts Finder.
Lowest contract
£102,592
Middle value
£269,753
Highest contract
£424,995
Contract periods ending by early September
7 of 9
Which contracts are in the study?
Every science lab refurbishment we found that Hampshire County Council let through its minor works framework and published as an award on Contracts Finder from 2021 to 2024. Values are as published and exclude VAT. We have not named the contractors.
| School | Work | Dates | Contract value |
|---|---|---|---|
| The Toynbee School | Science lab refurbishment | 28 June 2021 to 23 August 2021 | £102,592 |
| Henry Cort Community College | Science lab refurbishment | 28 June 2021 to 23 August 2021 | £123,887 |
| Portchester Community School | Science lab refurbishment | 26 July 2021 to 12 November 2021 | £424,995 |
| Brookfield Community School | Science lab refurbishment | 20 June 2022 to 29 August 2022 | £261,479 |
| Henry Cort Community College | Science lab refurbishment, phase 2 | 20 June 2022 to 29 August 2022 | £269,753 |
| Crestwood Community School | Science lab refurbishment, phase 2 | 25 July 2022 to 17 October 2022 | £299,850 |
| Horndean Technology College | Science lab refurbishments | 15 May 2023 to 30 August 2023 | £379,079 |
| Hamble School | Science laboratory refurbishment | 3 July 2023 to 28 August 2023 | £316,685 |
| Frogmore Community College | Science labs refurbishment | 15 July 2024 to 2 September 2024 | £173,429 |
What does it show about cost?
The range is wide because the jobs are different sizes. Four of the nine were described as more than one lab or as a second phase, but the highest value, £424,995, was a single scheme at one school that ran from July into November. Most notices don't give floor areas or room counts, so the value alone doesn't tell you the rate per room.
What the figures do give you is scale. A science lab refurbishment let by a council is a six-figure contract, and the middle job in this set was £269,753. Treat that as a guide when you set a budget, not as a price for your rooms.
What does it show about timing?
All nine contract periods started between May and July. 7 were scheduled to end by the first days of September, in time for the new school year. These are the planned dates in the award notices, not records of when the work finished.
The other two ran to October and November, and one of them was the largest contract in the set. If your scheme covers several labs, plan for a phase that carries on after the holiday, with the noisy work kept out of lesson time.
Read more in our guide to science lab refurbishment.
How did we collect it?
We searched Contracts Finder, the government's register of public contracts, for awarded notices describing science lab refurbishments at schools. Hampshire County Council publishes awards from its minor works framework in a consistent way, which made it possible to compare like with like. We opened each notice and took the value, the start and end dates and the description as published.
Other councils and academy trusts let similar work, but many publish fewer details or use frameworks that don't post each call-off, so we kept to one consistent source.
Planning a lab of your own? Get a quote from a contractor who works near your school.
Get a quoteGet a quote for your science lab
Four boxes: the school postcode, who to ask for, a phone number and an email. That is enough for us to get going.
School Refurbishment Contractors is an independent matching service. We look for a refurbishment contractor that covers the school's area. You get the contractor's name first, and your details stay with us until you say yes. The school pays nothing.
Got it. We're on it.
What happens next:
- We search for a contractor that covers the school, then email you their name.
- You give the go-ahead, or tell us to stop. Nothing moves without your say.
- The contractor calls to book a visit to the rooms and then sends a written price.