Science Lab Refurbishment
New benches, services and extraction for school science labs and prep rooms, built over the summer so the department starts the year in a working room.
When is a lab due for refurbishment?
Most schools don't plan a lab refit because the rooms look tired. They plan it because something has stopped working. The gas taps leak or have been capped off, the sinks drain slowly, the benches are swelling at the joints, or the layout makes it hard to see what thirty students are doing at once.
Another common reason is the timetable. If one department has grown and another has shrunk, a general classroom can become a lab, or two small labs can become one larger teaching space with a shared prep room.
Whatever the reason, write down what isn't working before anyone draws a layout. It keeps the brief honest and makes quotes easier to compare.
Middle contract value in our lab study
£269,753
From 9 science lab refurbishments let by one county council between 2021 and 2024. See all nine.
What does a lab refurbishment include?
Not every job needs all six. A price should list each one separately so you can see where the money goes.
Strip-out
Old benches, sinks, service runs and floor coverings out, with the gas made safe and capped by someone qualified to do it.
Services
Gas, water, drainage and power renewed to the new layout. It is usually the biggest single line in the price, and the riskiest.
Benching and storage
Perimeter benches, island or peninsula layouts, sinks, chemical-resistant worktops and lockable storage.
Extraction
Fume cupboards where the department needs them, ducted out of the building, plus general ventilation for the room.
Ceilings, lighting and floors
A new ceiling grid and LED lighting, safety flooring and decoration once the wet trades are done.
Prep room
Often forgotten in the budget. Technicians need sinks, storage, a dishwasher or glassware washer and somewhere safe for chemicals.
How do you get it done over the summer?
The holiday is about six weeks, and the building work fits into it only if everything before it happens on time. Here is the plan that works for most schools.
By Easter
Layouts agreed with the head of science and the technicians, a measured survey done and the price in. Fume cupboards and benching can have long lead times.
Summer term
Contract signed, asbestos information checked, the order placed and the rooms emptied before the last week of term.
Summer holiday
Strip-out, services, benching and ceilings. The noisy and dusty work all happens while the school is empty.
Start of term
Gas and extraction tested, the room cleaned and handed over, with snagging done after school if needed.
If the order slips into July, talk to the contractor straight away about phasing. A two-stage job, with one lab in the summer and the next at Easter or the following summer, is better than a rushed finish in September.
What makes a good lab layout?
The teacher needs to see every student and reach every station quickly. Perimeter benches with a clear middle work well for demonstrations. Islands or peninsulas give more working space but need services brought up through the floor, which costs more.
Think about where the gas and water come up, where students wash their hands, where bags go, and how a wheelchair user gets to a working station at the right height.
What should the quote show?
Ask for the strip-out, services, benching, extraction, ceilings and lighting, flooring and decoration as separate lines. Ask what is excluded: loose stools, technician equipment, asbestos removal and any work in the prep room.
If two quotes look very different, the gap is usually in services and extraction. That is the line to ask about first.
Planning a lab refurbishment for next summer? Get a quote now while there's time to order.
Get a quoteWhat do schools ask?
How much does a science lab refurbishment cost?
In our data study of nine council-let jobs, the contract values ran from £102,592 to £424,995, with a middle value of £269,753. Several of those covered more than one lab. A single room with new benches and services sits at the lower end.
Can a lab be refurbished in the summer holidays?
Usually, if the order is placed early. 7 of the 9 jobs in our study had contract periods ending by the first days of September. Of the two that ran into term, one was the largest contract in the set.
Do we need new fume cupboards?
Not always. Some departments refurbish around the existing cupboards and only replace the ductwork or controls. Ask the contractor to look at what is there and price both options.
Who should be involved in the design?
The head of science and at least one technician. They know how the rooms are actually used, where the gas taps get in the way and how many students need to work at once.
Can one lab be done while the others stay in use?
Yes, and it is common. The contractor fences off the room being worked on, plans deliveries around lesson changes, and isolates services so the other labs keep gas and water.
Get a quote for your science lab
Four boxes: the school postcode, who to ask for, a phone number and an email. That is enough for us to get going.
School Refurbishment Contractors is an independent matching service. We look for a refurbishment contractor that covers the school's area. You get the contractor's name first, and your details stay with us until you say yes. The school pays nothing.
Got it. We're on it.
What happens next:
- We search for a contractor that covers the school, then email you their name.
- You give the go-ahead, or tell us to stop. Nothing moves without your say.
- The contractor calls to book a visit to the rooms and then sends a written price.