Fitting a School Refurbishment Into the Summer Holidays

Planning · 17 November 2026 · 2 min read · By School Refurbishment Contractors

The short answer

Often, yes, if it is ordered in good time. Seven of nine council science lab refurbishments we looked at had contract periods ending by early September. Bigger jobs, like a whole block, usually start in the summer and carry on into term in phases.

The summer holiday is the one long stretch when a school is empty. That makes it the obvious time for building work, and it means every school wants it at once.

So the question isn’t really whether the work can be done in the summer. It is whether you can get everything ready in time.

What do real jobs show?

We looked at nine science lab refurbishments that Hampshire County Council let between 2021 and 2024, using the award notices it published.

All nine contract periods started between May and July. Seven were scheduled to end by the first days of September. The other two ran to October and November, and one of them was the largest contract in the set.

You can see every job in our science lab data study.

How long do bigger refurbishments take?

Longer than a holiday. The national school cost benchmark, put together by councils and the DfE, found the average primary school refurbishment contract lasted 34 weeks.

That doesn’t mean 34 weeks of disruption. It means the work is phased, with the noisy parts in the holidays and the rest planned around lessons.

When should you start planning?

Earlier than feels necessary. Here is a rough timeline that works for most summer jobs:

  • Autumn term: agree what needs doing and roughly what it might cost
  • Spring term: get a site visit and a written price, and check your procurement rules
  • By Easter: sign the order, so materials with long lead times can be made
  • Summer term: empty the rooms and agree the site set-up
  • Summer holiday: the building work

If you are only starting in June, talk to a contractor straight away. A smaller first phase this summer is often better than a rushed whole job.

What usually goes wrong?

Most late finishes come down to a handful of things. These are the ones to watch:

  • Benching, fume cupboards or windows ordered too late
  • Asbestos found once the ceilings come down
  • Decisions on layout or finishes still being made in July
  • No plan for what happens if the work runs into term

The last one matters most. Agree with the contractor, before work starts, which rooms you need back on the first day and what can wait.

Want a price in time for next summer? Tell us where your school is and we’ll find school refurbishment contractors who work near you.

Sources

Get a quote for your school

Four boxes: the school postcode, who to ask for, a phone number and an email. That is enough for us to get going.

School Refurbishment Contractors is an independent matching service. We look for a refurbishment contractor that covers the school's area. You get the contractor's name first, and your details stay with us until you say yes. The school pays nothing.

Your school and how to reach you

By sending this form you agree that we'll use your details to find a local school refurbishment contractor for you. We'll tell you who they are and ask you before passing your details on. See our privacy policy.

Get a quote